Jameson Canyon Construction 7_10_14

Construction crews work on a raised median on the Solano County section of Highway 12-Jameson Canyon Road, Thursday. The construction is projected to be finished by early September. (Robinson Kuntz/Daily Republic)

Solano County

Highway 12 widening could finish in early September

By From page A1 | July 11, 2014

FAIRFIELD — State transportation officials can now speak the words that motorists commuting on Highway 12 through Jameson Canyon have long been waiting to hear.

“We are nearing the end of the project,” state Department of Transportation Senior Transportation Engineer Elias Moussa said Thursday.

The target date to finish major work is Sept. 5, Moussa said. But, he added, the unexpected could happen and this date is tentative.

What’s clear is that, though the precise day might vary, the end of the road is in sight for the Highway 12 widening project.

The $130 million project began construction in spring 2012 and extends 6 miles from Interstate 80 in Solano County to Highway 29 in Napa County. Caltrans is transforming a road that was two lanes for most of its length into one that is four lanes and is adding a concrete median barrier. Its stated goals are to improve traffic flow and safety.

Work on the 3-mile Napa County segment for the most part wrapped up in April and motorists since have been able to use all four lanes there, two in each direction. But the 3-mile Solano County segment is taking longer and remains only two lanes, one in each direction.

The reason: a hill towered above the old version of the highway in Solano County, with the steep slope hugging the roadway’s side. To make room for the extra two lanes and shoulders, workers had to remove a large portion of the hill. They trucked away 340,000 cubic yards of dirt and rock.

“This basically is the project for Solano County,” Moussa said as he stood near the hill.

Workers have created a massive, three-tier retention wall along a half-mile stretch of the carved-out hill. At the highest point, the wall is broken into tiers that are 20 feet tall, 55 feet tall and 55 feet tall, for a total of 130 feet. The cement walls have been sculpted and stained to resemble rock.

Ultimately, two eastbound lanes will run at the base of the lower retention wall and two westbound lanes will run along a shelf carved out along its top. At one point, the eastbound lanes will be 20 feet below the westbound lanes.

Since mid-January, both eastbound and westbound traffic have used the two lanes on the upper shelf. Workers on the lower roadbed section have been largely out of sight as they’ve done such things as work on the lower retention wall and replace a Vallejo water line.

This past week, workers have been paving. Through Thursday morning, they had put down 7,000 tons of asphalt that came from the Syar Industries Lake Herman Quarry near Benicia, with 3,000 tons to go.

The next milestone for motorists is scheduled Aug. 1. Then the one lane of eastbound traffic is to shift to the right-hand lane of the lower section that workers are paving. Westbound traffic will remain in the right-hand lane of the upper shelf. The left-hand lanes on both levels will be used by workers as they top the first-tier retaining wall with a median barrier.

A final step will be putting down a layer of rubber asphalt on the pavement on both levels and doing the permanent striping.

When final paving was done on the Napa County side several months ago, work took place during the day because temperatures were too low at night for paving. That in turn caused traffic delays. On a few of the worst days, it took an hour to drive the 6 miles from Interstate 80 to Highway 29 in the afternoon.

But Moussa expects only minor delays as the Solano County side wraps up. Higher temperatures during the summer allow for paving to be done at night.

Reach Barry Eberling at 427-6929 or [email protected] Follow him on Twitter at www.twitter.com/beberlingdr.

Barry Eberling

Barry Eberling

Barry Eberling has been a reporter with the Daily Republic since 1987. He covers Solano County government, transportation, growth and the environment. He received his bachelors of art degree from the University of California, Santa Barbara and his masters degree in journalism from the University of California, Berkeley.

Discussion | 6 comments

The Daily Republic does not necessarily condone the comments here, nor does it review every post. Please read our Terms of Service and Privacy Policy before commenting.

  • John AndersonJuly 11, 2014 - 6:46 am

    That's GREAT NEWS!. Then they can get to work on improving the even busier stretch of 12 from Suisun City to Lodi- you know- that miserable, dangerous little 2-lane shortcut mobbed by big-rigs and so many travelers which still looks like it did in the 1940s!

    Reply | Report abusive comment
  • Mr. PracticalJuly 11, 2014 - 7:39 am

    John,what would you propose they do?

    Reply | Report abusive comment
  • caligirl12July 11, 2014 - 10:07 am

    that stretch is not wide enough in spots to make wider.. If drivers would pay more attention and not be in so much of a hurry it wouldn't be an issue. this stretch fron 80 to 29 is well worth the wait. I drive it everyday from Suisun to work ... Thank you to all who worked hard getting it completed...

    Reply | Report abusive comment
  • keenplannerJuly 11, 2014 - 3:31 pm

    Don't hold your breath. That section would require extensive environmental work, and large sections of causeway, since it traverses wetlands and delta areas. The cost/benefit analysis is bleak, and CA doesn't need any more car traffic.

    Reply | Report abusive comment
  • omydarling21July 12, 2014 - 12:07 pm

    I agree with both John Anderson and keenplanner. I thought they were talking about Highway 12 from Suisun to Stockton. Sigh... no hope. 1 more lane on each side would be highly appreciated though.

    Reply | Report abusive comment
  • omydarling21July 11, 2014 - 11:48 pm

    Writers! Please learn to condense! Short, sweet, fact full, and to the point would be highly appreciated.

    Reply | Report abusive comment
  • Recent Articles

  • Enter your email address to subscribe and receive notifications of new posts by email.

  • Special Publications »

    Use of this site constitutes acceptance of our Terms of Service (updated 4/30/2015) and Privacy Policy (updated 4/7/2015).
    Copyright (c) 2015 McNaughton Newspapers, Inc., a family-owned local media company that proudly publishes the Daily Republic, Mountain Democrat, Davis Enterprise, Village Life and other community-driven publications.